Week Commencing 02nd March & 09th March
This week we finished plasterboarding the first floor extension.
Firstly we constructed the partition wall to create two bedrooms and then we started to Tape and Joint the plasterboard in what was the master bedroom that has been split to make two equal size bedrooms. Prior to painting.
We also continued to tape and joint the plasterboard in the new master bedroom within the extension. Prior to painting.
Towards the end of this week the three bedrooms were ready for painting each room painted white for crispness with one wall highlighted with a colour to work with the child’s colour scheme they have requested.
We also began to strip the wall paper from the landing to make way for painting.