Week Commencing 17th February 2020
The roof has been battened, finished with the membrane and now nicely tiled including the hip that our first builder had advised was not required even though it was on my planning approval, the feeling of getting a roof and walls with insulation installed is immense. It is definitely feeling like the end is in sight.
All the timber frame has been lined with OSB and then finished externally with fire-board to ensure for a minimum of 30mins fire protection. The guys came back to install the breather membrane and battens ready for the installation of the render.
All internal walls have started to be constructed to give a framework for the individual rooms.
All walls have had the insulation put in ready for plasterboarding.