Week Commencing 6th January – Preparation work for plastering. All remainder steels have been boxed in with 2 layers of Gyproc Fireboard this is to prevent the passage of fire. The Gyproc Fireboard is a Pink Board.
Two guys got the ceilings and walls plastered within the living room, dining room, kitchen and hall. This gives it a fresh new feel without too many imperfections.
The new kitchen installation took place on the 9th January and we have been advised that the work will take approx. 4 to 5 days to complete. The guy set out all the units first this took the first two days.