Expanding Spaces – Making a House a Home – Block work to Ground Level

Day Six – Ten – 4th – 8th November (week 2)

Building Regulation Requirement:

Ground Floor wall construction.

  • 102.5mm Facing Brick work
  • 100mm Cavity with GA4000 Insulation or similar
  • 100mm 7N Aerated Blockwork

Blockwork to GL

Dave and Steve carried out the next stage of construction …

That is to construct the block-work from top of foundations up to GL this will give a platform for the next stage of the build the facing brick work up to DPC. Then they went from Ground Level to DPC (damp proof course) with Facing Brickwork this is because we are having weatherboarding so from GL (ground level) to DPC this face will be visible.

 

Published by

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s